DETEC Announces Planned Outages Starting Oct. 21st

October 19, 2021 - In order to complete system reliability improvements, Deep East Texas Electric Cooperative will have the following planned outages. These outages are necessary to ensure the safety of our crews while working. We apologize for the inconvenience during these times. All members of these substations will receive an automated call the day prior to their outage. There is no need to report your outage during these times. Should you have any questions, please call 936-229-4000, option #2.

Thursday, October 21st beginning at approximately 8:30 until 10:30 AM

  • Center South Substation – areas of Highway 7 W, FM 138, Loop 500, Hwy 96 S of Center, Arcadia, Spann Chapel, Goodhope, Short, Shelbyville, and the areas surrounding these locations. *Please note that the Shelbyville ISD School circuit will be rerouted to provide power to the school during this time. The school WILL NOT experience the outage.

Friday, October 22nd beginning at approximately 8:30 AM until 11:30 AM

  • Hurstown Substation – areas of Patroon, East Liberty, Dreka, Brinson Marina, North of Lout Town, and the areas surrounding these locations 

Friday, October 22nd beginning at approximately 8:30 AM until 9:30 AM and a short blink at approximately 11:30 AM

  • Huxley Substation – areas of Rolling Hills, Huxley Bay Marina, Doyle English Marina, and the areas surrounding these locations

Saturday, October 23rd beginning at approximately 7 AM until 10 AM

  • Center Substation – areas of: Campti, Sardis, 699 toward Paxton, Hwy 7 E toward Joaquin, 96 N, 87 N, Enterprise, Fulstom Chapel and the areas surrounding these locations