CR 4778 Bridge Re-deck Project Complete

April 8, 2025 - Commissioner Bellmyer reports that the CR 4778 bridge re-deck project is complete.

The road is now open to all traffic.


April 2, 2025 - The work proposed to be done on CR 4778 has been rescheduled due to weather forecast to take place on the originally planned weekend. Commissioner Bellmyer has updated the work plans to now reflect that they will take place on Monday through Wednesday, April 7-April 9. Commissioner Bellmyer will be informing the school and post office to allow them the ability to take that work into account.


March 26, 2025 - Tom Bellmyer, Commissioner Precinct 4, has announced that County Road 4778 will be closed April 4-April 6 for the purpose of redecking a bridge.